On June 13, 2014, the Department of Conservation (“Department”)  issued a public notice and posted the latest version of the proposed regulations for the use of well stimulation in oil and gas production (“Revised Proposed Regulations”).  These are revisions to the permanent regulations that will go into effect on January 1, 2015.  The Revised Proposed Regulations include the following, significant changes:Continue Reading Department of Conservation Issues Revised, Proposed Well Stimulation Treatment Regulations

In SPRAWLDEF et al. v. San Franscisco Bay Conservation and Development Commission, et al. (“SPRAWLDEF”)(certified for publication 5/28/2014), the First Appellate District reversed the trial court’s decision and held the San Francisco Bay Conservation and Development Commission’s (“Commission”) determination that a project alternative was not economically feasible was supported by substantial evidence.

The California High Speed Rail Authority’s (the “Authority”) Board of Directors unanimously voted on Wednesday to certify the Final Environmental Impact Report/Environmental Impact Statement for the Fresno to Bakersfield alignment of the high-speed rail project (the “Project”) and approve the selected alignment.  Click HERE for a map of the approved alignment.  The Federal Railroad Administration

At one time or another, in almost every jurisdiction around the state, on the day before an important project land use hearing, an opponent of the project has submitted a lengthy comment letter (often accompanied by voluminous attachments) alleging that the environmental analysis does not comply with the California Environmental Quality Act (CEQA).  The lead

In Ctr. for Biological Diversity v. Dep’t of Fish & Wildlife, No. B245141 (Cal. Ct. App. 2d Dist. Mar. 20, 2014), the appellate court reversed the trial court’s decision, which found that the Department of Fish and Wildlife’s (“Department”) certification of an environmental impact statement and report (“EIR”) was “not supported by substantial evidence.”  In a sprawling 117-page, published Opinion, the appellate court rejected the notion that a 5,828-page, project level EIR, which did not approve any specific construction, was insufficient.

We focus only on the Department’s challenged certification of the EIR, which studied a resource management plan, conservation plan, and streambed alteration agreement, as well as the issuance of incidental take permits under California’s Endangered Species Act (“CESA”).  The underlying Newhall Ranch project, a specific plan approval in Los Angeles County, would allow residential, mixed-use, and non-residential land uses and provide up to 21,308 dwelling units, essentially building a new city.  The trial court found, among other things, that the Department “failed to conduct an independent review of project impacts,” that many of its findings were not supported by substantial evidence, and that it failed to prevent the taking of the Unarmored Threespine Stickleback (“stickleback”), a fully protected fish under CESA.Continue Reading Court Clarifies “Taking” Of Endangered Species And Highlights What’s “Enough” Under CEQA

In his SB 4 signing message (see September 20, 2013 post), Governor Brown promised certain “clarifying” amendments for SB 4, and his administration has begun the process of seeking those amendments.

Governor Brown’s proposed legislation would amend SB 4 in three major categories:

Permanent Regulations

  • DOGGR’s deadline for draft permanent regulations will be

In Trisha Lee Lotus v. Caltrans (Jan. 30, 2014), the First District Court of Appeal reversed a Humboldt County Superior Court decision, and ruled that a California Department of Transportation (Caltrans) environmental impact report (EIR) failed to adequately analyze the significance of the project’s impacts to old-growth redwood root systems in a state park.

Caltrans prepared the EIR for the realignment of a 1-mile segment of U.S. Route 101 that passes through Richardson Grove State Park, which is home to old growth California redwoods.  The project’s goal is to accommodate standard-sized trucks that have been restricted from using the road due to its size and configuration.  Petitioners-appellants, including the Environmental Protection Information Center, the Center for Biological Diversity, and Californians for Alternatives to Toxics (jointly, “Lotus”), challenged the adequacy of the EIR on several grounds, and won on appeal on one issue.Continue Reading Caltrans EIR Analysis of Impacts to Redwoods Found Inadequate

In Protect Agricultural Land v. Stanislaus County Local Agency Formation Commission (filed January 28, 2014) (“Protect Agricultural Land”), the Fifth District Court of Appeal affirmed judgment on the pleadings in favor of the Stanislaus County Local Agency Formation Commission (“LAFCO”), and squarely held that all “lawsuits seeking to set aside a LAFCO approval

Environmental groups will have to wait to challenge hydraulic fracturing activities in the state of California until the Division of Oil, Gas, and Geothermal Resources (“DOGGR”)  issues its permanent regulations in 2015.  This is according to Alameda County Judge Evelio Grillo, who on January 17, 2014, granted a motion to dismiss a challenge brought by

In City of Irvine v. County of Orange (“City of Irvine”) (published and modified on November 22, 2013), the Fourth District Court of Appeal affirmed the trial court’s ruling that the County of Orange’s (“County”) application for state funding for jail expansion was not a “project” requiring environmental review pursuant to CEQA.

In